Validation
Following our tickIT and GAMP based audited quality procedures, we perform three stages of tests on all projects. Factory Acceptance Test (FAT), Installation Qualification (IQ), and Operational Qualification (OQ). Our system is flexible and can be refined to customer's requirements e.g. SAT Testing etc.
The FAT uses an approved document to check if the build is to an acceptable standard.
The IQ is used to ensure that system installation is performed to an acceptable standard.
The OQ is the final stage where the systems are tested and commissioned using the plant. The OQ document is created from the requirements of the users specification; this will ensure all items of the system are tested for compliance with the specification. The system is then approved to hand over to the client for PQ (Process Qualification).
All of these documents are traceable to the design documents.
Validations and qualifications are an essential part of work in high integrity markets such as pharmaceuticals, Food/Beverage and Aeronautics.
Silchester has many qualified validation staff and partner a number of specialised consultants in industry. Retrospective validations and design stage validations are very much in demand. Silchester has many years experience in this field and aim to exceed your requirements.